MISTRAL NEWS (July 1st, 1997) After the shut-down of the spectrometer at Orsay (April 7) and the transportation to CERN (April 29), the installation of the set-up on line to the ISOLDE beam line in the new extension has taken place. This installation is now completed and since last week, the beam from the auxiliary ion source is available . Currently, the setting-up of the trajectory into the spectrometer is beginning. During summer, the experiment will be attended continuously. The time schedule is the following: July: - setting-up of the trajectory, - operation of the software for the control of the parameters. August: - optimization of the beam transmission through the spectrometer, - setting-up of the ISOLDE beam injection into the spectrometer (ISOLDE stable beam, week 34) September: - operation of the softwares: data acquisition, on-line and off-line data analysis, - survey of systematic errors, in addition to the tests already made in Orsay. October: - global optimization. November: - 1st run for data taking with the radioactive beam (Ne): some beam time during weeks 47 and 48.